Horizon 3023
We are nearly at the finish line with this project! The project team have worked tirelessly since July 2019 to complete these works for our client, Dexus.
Works have included the upgrade of the existing Palm Springs Road; including but not limited to earthworks, stormwater drainage and pavement re-construction, as well as the construction of a new subdivision, consisting of earthworks, stormwater drainage, water reticulation, sewerage reticulation, electrical reticulation, street signage and pavement construction.
With the final stages of construction well underway, the team is preparing for the last electrical sign off and Council practical completion.