Our Windermere project team have had a busy start to the year!

The team has successfully completed the asphalt for Stage 18, with a total of 542 tonnes laid and additional works including:

  • 3623sqm of Prime/Sami
  • 1185Lm of kerb
  • 1801 SQM of footpaths/driveways.

We’re also proud to announce the completion of Windermere IN05, which includes:

  • 5371 tonnes of asphalt
  • 1924Lm of kerb
  • 3128sqm of footpaths/islands/bus bays, and
  • a signalised intersection.

These works will contribute to improved infrastructure and a more connected community.

In addition, Windermere Stages 11 & 12 have just received EDLP (End of Defects Liability Period) sign-off from council with no defects found, the stages have now been handed over to council control!

Thank you to our dedicated project team for their hard work on the Windermere Estate project for Risland Australia